Turf installation ahead of schedule at GB Sports Complex

Posted Oct 07, 2021 12:00 PM

By COLE REIF
Great Bend Post

The City of Great Bend and Great Bend Recreation Commission held another monthly meeting with Hellas Construction last week to receive an update on the artificial turf installation at the Great Bend Sports Complex.

City Administrator Kendal Francis did not want to jinx the progress but told the Great Bend City Council that the project is roughly a month ahead of schedule.

"It is progressing well," said Francis. "It has been interesting to see how that stuff is put together. On paper, we're about five percent ahead of schedule."

The $1.36 million project will install turf on the infields and bullpen areas at the four Sports Complex fields and nearby Langrehr Field.

Hellas has until Feb. 1, 2022 to complete the installation.

The Rec committed $200,000 and annual maintenance of the fields and the Great Bend school district pledged $280,000. The city is responsible for the remaining cost.